Dent Co Crossing South Slope Protection

 














Arrived at 10:30 am and Contractor was ready to pour South Slope Protection. First truck arrived at 11:25 am, I tested the concrete; Air 5.5%, Slump 3/4", Temp 78°. We started pour, made three cylinders.

















Pour went well, contractor will finish up rip rap and dirt work and will be waiting on tree planting and walk through.