4259 Dent Co Box Culvert Floor Pour

 











Arrived onsite at 7:30, Contractor was finishing up forms and gathering equipment for the pouring of the floor of the box culvert. First five trucks had Air issues. Bad Air pod at plant, Pour went well other than Air Issue.











Form work and rebar placement was good. first Truck arrived at 7:40, Had to add air and finally rejected it do to low Air 3%.











Finished pour around 1:00 pm, made two sets of Cylinders. Next pour will be at the first of next week.











Ended up being short, had to call for a couple yards to finish.