Arrived onsite at 10:25 am, Schrimpf Landscaping was onsite to Seed and Plant Trees. Machine is loaded and ready to start spreading seed and mulch. Seeding and Mulch finished, starting on Tree Planting.
Arrived at 10:30 am and Contractor was ready to pour South Slope Protection. First truck arrived at 11:25 am, I tested the concrete; Air 5.5%, Slump 3/4", Temp 78°. We started pour, made three cylinders. Pour went well, contractor will finish up rip rap and dirt work and will be waiting on tree planting and walk through.
Contractor was ready to pour South approach slab. Concrete arrived at 11:25 am, I tested concrete; Air 7%, Slump 3-3/4", Temp 74°. Started pour. Finished pour, went well, made three cylinders and will pour south slope protection.
Arrived at 10 am to pour North Slope Protection. Concrete arrived at 12:13 pm, I tested concrete; Air 4.9%, Slump 1-1/2", Temp 70°. Started pour, made three cylinder. Pour went well, will pour south side approach slab and protection next week.
Arrived at 12:40 pm to pour North approach slab, contractor was ready. Concrete arrived and I tested; Air 7%, Slump 4-1/2", Temp 70° Started pour Finish and will pour Slope protection tomorrow.
Arrived at 8:15, checked forms and rebar placement. Setup to test Concrete. Air:7%, Slump:4-1/2”, Temp:82. Made three cylinders. Contractor plans to let it set for a week to let cure, then start on approaches.